Modernization and reconstruction of the Hungarian - Serbian railway on the territory of the Republic of Serbia, section Belgrade Center - Stara Pazova 

Project carrier: 

Ministry of construction, transport and infrastructure,

"Infrastructure of the Railways of Serbia" j.s.c.

Project title: 

Modernization and reconstruction of the Hungarian - Serbian railway on the territory of the Republic of Serbia, section Belgrade Center - Stara Pazova

 

Investor: 

"Infrastructure of the Railways of Serbia" , j.s.c.

Financier: 

Ministry of construction, transport and infrastructure

Contractor: 

Joint Venture of China Railway International Co.Ltd & China

Communications Construction Company Ltd

The significance of the project: 

The project is part of the most important infrastructure projects in Serbia implemented in cooperation with People's Republic of China, Russian Federation and Republic of Hungary within the 16 + 1 initiative "One Road, One Belt".

 
Investment value: 

350.162.540,00 USD

Start of the project: 

June 5th 2018

Completion of the project: 

June 5th 2021

Project description: 

The works are carried out and they are in accordance with the planned dynamics of the works. There are no indications of an increase in the contracted deadline.

- Works on the lower machine of the railway are in progress, especially in the area of Novi Beograd station.

- The works of filling and compression of the transverse layer of the railway line on Belgrade Center - Zemun section, are carried out

- Preparation works for the construction of a roadway at the location of Tosin bunar is in the process.

 

The project involves the design phase (construction permit project, construction project), construction, procurement, delivery and installation of all elements necessary for modernization, reconstruction and construction of the railway line at Belgrade Center - Stara Pazova 34.5 km length, reconstruction of the existing double-track lines and the construction of new freight traffic routes on Batajnica - Stara Pazova route, in order to establish an electrified double-track line for mixed traffic speeds up to 200 km / hour in accordance with the requirements of the basic corridor Trans-European Transport Network (TEN-T) and comply with technical specifications for interoperability (TSI).