Reconstruction of the section Jajinci – Mala Krsna and renovation of the Mala Krsna station
Serbian Railways Infrastructure a.d.
Reconstruction of the section Jajinci – Mala Krsna and renovation of the Mala Krsna station
Serbian Railways Infrastructure a.d.
Consortium “COLAS Rail” and “Energorprojekt”
Consortium “COLAS Rail” and “Energorprojekt”
Institute of Transportation CIP
The objective of the Project of Reconstruction of the section Jajinci – Mala Krsna is improvement of the railway infrastructure on Corridor Х, in view of the fact that this is one of the most important and also busiest railway routes through the Republic of Serbia.
Works are underway during a complete suspension of railway transport.
- Percentage of physical realization on 21 May 2021: 88.04%
- Percentage of financial realization on 21 May 2021: 73.07%
39,253,214.30 EUR
39,253,214.30 EUR
Project Completion Date is to be late July 2021.
The Project is funded by a loan from the European Bank for Reconstruction and Development.
The Project includes renovation of the railway section from the Straževica Tunnel (entrance) - Jajinci - Mala Кrsna and Mala Кrsna Station, length: 60.8 km (with no auxiliary tracks at the station), at the railway (Belgrade) Rakovica – Rasputnica К1 – Mala Кrsna – Velika Plana.