Contractual Agreement for the Project of Infrastructure Construction and Embankment of the Metro Depot in Makiško Polje, Belgrade

Project carrier: 

Ministry of Construction, Transport and Infrastructure

Project title: 

Contractual Agreement for the Project of Infrastructure Construction and Embankment of the Metro Depot in Makiško Polje, Belgrade

Contracting Authority: 

Government of the Republic of Serbia, Ministry of Construction, Transport, and Infrastructure of the Republic of Serbia (Financier) City of Belgrade, City Secretariat for Communal and Housing Affairs, and Public Enterprise "Directorate for Construction Land and Development of Belgrade" (Investor)

Main contractor: 

Power Construction Corporation of China Limited Belgrade branch

Investor: 

City of Belgrade – City Secretariat for Utility and Housing Affairs and the Public Enterprise Directorate for Construction Land and Urban Development of Belgrade

Contractor: 

Power Construction Corporation of China Limited Belgrade branch

Designer: 

N-ING doo

The significance of the project: 

The implementation of the contractual agreement will provide the necessary infrastructure conditions for the Makiš Depot, from which Lines 1 and 2 of the Belgrade metro will be managed. It will serve for the parking of rolling stock for Lines 1 and 2 of the Belgrade metro, as well as for the maintenance of the entire future metro network, which will consist of three lines.

Status of the project: 

Phase "0" – "Construction of the embankment for the metro depot" was completed on November 8, 2024.  Works are currently being carried out to remedy the deficiencies listed in the snag list provided by the Engineer.

Investment value: 

Estimated value: 85,9 million euros

Source of finance: 

RS budget

Project description: 

For the needs of the metro line and metro depot, an embankment made of reclaimed sand has been constructed, consisting of approximately 1.5 million cubic meters of sand over an area of 72 hectares. For the purpose of stormwater evacuation, two reinforced concrete collectors, a pumping station, and a transformer station to supply power to them have been constructed.