Corridor 10, E-80, Nis - border with Bulgaria (Eastern fork)

 

Eastern fork of Corridor 10, E-80, from Nis to the border with Bulgaria in the length of 86,9km is composed of 10 LOTS:

 

Prosek-Bancarevo road and bridges LOT 1 (contractor AKTOR SA, Terna SA, contracted value 36.22 million euros, works completed on 30. 9. 2017), the share from technical means was not entered into the traffic, was released on finished works at the assembly of Bancarevo-Crvena Reka and arranged tunnel Bancarevo EMI

Bancarevo-Crvena Reka LOT 2 (contractor AKTOR S.A, established value of 39.92 million euros. Expected completion and release of the section for traffic period in 2019

 

 

Problems: a large number of unstable slopes that are slowing down the works (on a section of a total of 27 slopes)


Prosek - Crvena Reka LOT 3 tunnel Bancarevo (contractor Subterra, contracted value of 20.4 million euros. Completed construction works. The installation of electromechanical installations is being carried out by Azvirt, the contractor)


Crvena Reka - Ciflik LOT 4 (the contractor is AKTOR S.A, the contract value of 43.04 million euros, the shares were put into public transport under the final layer of asphalt on 7. 7. 2017)


Ciflik - Stanicenje LOT 1 (the contractor is Construcciones Rubau, the contracted value of the works is 31.3 million euros, the sections were put into public traffic under the final layer of asphalt on July 13th, 2017)


Stanicenje - Pirot east LOT 2 (the contractor is AKTOR SA, the contracted value of the works is 69.4 million euros, 7.4 km of the section released into public traffic under the final layer of asphalt in the full profile on Septmeber 16th 2017, 5, 0 km in full profile on 18th of March 2018, the section is partially completed and released for traffic, but parts of the section in the tunnel Sopot and Sarlah are not. Equipping the tunnel Sopot and Sarlah with electromechanical installations is being carried out.


Bela Palanka - Pirot LOT 3 parallel non-commercial road (the contractor is Trace Group Hold plc, contract value of 15.4 million euros, works completed on April 15th, 2018)


Pirot East - Dimitrovgrad LOT 1 and LOT 2 (the contractor is Trace Group Hold plc, contracted value of 19.5 million euros, section was put into traffic on September 16th , 2017)


Bypass Dimitrovgrad LOT 1 and LOT 2 - (After the termination of the contract with Alpine, a contract was signed with Trace Group Hold plc in May 2016. A new contract was signed with the contractor AKTOR S.A)

The value of completed works with "Alpina" is 19.83 mil. euros
 
The value of the works carried out with "TRACE" is 2,87 mil. euros
 
The value of contracted works with "Aktor" is 17,068 mil. euros
 
The section was released for traffic under the final layer of asphalt in full profile on September 16, 2017, except in the area of ​​the slopes of Gradinje, where the traffic was released in full profile on March 18th, 2018. Works on rehabilitation of the unstable part of the slope are underway. Expected completion deadline is June 2019.


Tunnels Progon and Przojna Slope (contractor TERNA SA), contract value 41.01 million euros
This section was released for traffic after the final layer of asphalt, with electromechanical equipment in full profile on 16th of September 2017. The contractor has completely finished the elimination of defects and the engineer has issued a certificate for a good job execution.
 
The value of the contract for tunneling is 564.709.000 RSD. Contractor is "Elef".