Construction of infrastructure at the Makiško polje site
Ministry of Construction, Transport and Infrastructure
Construction of infrastructure at the Makiško polje site
Ministry of Construction, Transport and Infrastructure
Power Construction Corporation of China Limited Belgrade branch
City of Belgrade – City Secretariat for Utility and Housing Affairs and the Public Enterprise Directorate for Construction Land and Urban Development of Belgrade
Power Construction Corporation of China Limited Belgrade branch
“Beoexpert Design”
- Development Plan for Rail, Road, Water, Air, and Intermodal Transport for the Period 2015–2020- General Master Plan for Transport in the Republic of Serbia 2009–2027- Agreement on Economic and Technical Cooperation in the Field of Infrastructure between the Government of the Republic of Serbia and the Government of the People's Republic of China.- Memorandum of Understanding for the Construction of the Metro System in Belgrade dated 22 January 2021.- Contractual Agreement for the Design and Construction of Roads and Communal Infrastructure at the Makiško Polje Location – Phase I, LOT 1, between the Government of the Republic of Serbia, the City of Belgrade – City Secretariat for Utility and Housing Affairs, and the Contractor Power Construction Corporation of China, Limited, Belgrade Branch, dated 23 November 2023.- Contractual Agreement for the Design and Construction of Roads and Communal Infrastructure at the Makiško Polje Location – Phase I, LOT 2, between the Government of the Republic of Serbia, the City of Belgrade – City Secretariat for Utility and Housing Affairs, and the Contractor Power Construction Corporation of China, Limited, Belgrade Branch, dated 23 November 2023. - Direct contracting based on the intergovernmental agreement between the Government of the Republic of Serbia and the Government of the People’s Republic of China.
The implementation of Contractual Agreements LOT 1 and LOT 2 will provide the necessary transport and utility infrastructure conditions for the needs of the Makiš Depot, from which Lines 1 and 2 of the Belgrade Metro will be managed, covering a total area of 72 hectares. It will serve for the parking of rolling stock for Lines 1 and 2 of the Belgrade metro, as well as for the maintenance of the entire future metro network, which will consist of three lines.
The construction of Collector 3 for drainage of the future metro depot at Makiško Polje has been completed. Preparatory works for the construction of Collector 4 are currently underway. For the remaining six collectors, the preparation of the Execution Design (PZI) is currently underway. For the remaining parts of the Project—including roads, interchanges, structures, pumping stations, and electrical installations—the preparation of the Construction Permit Design (PGD) is in progress to support the issuance of construction permits.
EUR 167,7 million.
Budget of RS and domestic banks loans
In order to provide the missing infrastructure required for the future metro depot at Makiško Polje, and considering that the Makiš depot will serve for the maintenance of the Belgrade metro rolling stock as well as all necessary maintenance machinery, these Contractual Agreements will encompass the construction of internal and access roads, a complete drainage system, electrical infrastructure for power supply, and all other necessary works required for the commencement of the depot construction.