Design and construction of Metro Line 1

Project carrier: 

Ministry of Construction, Transport and Infrastructure

Project title: 

Design and construction of Metro Line 1

Јавни наручилац: 

Government of the Republic of Serbia, Ministry of Construction, Transport, and Infrastructure of the Republic of Serbia (Financier) City of Belgrade, Secretariat for Public Transport and Public Utility Company “Belgrade Metro and Train” (Client)

Главни уговарач: 

Power Construction Corporation of China Limited Belgrade branch

Investor: 

Republic of Serbia, Government of the Republic of Serbia, Ministry of Construction, Transport, and Infrastructure

Contractor: 

Power Construction Corporation of China, Limited and Power Construction Corporation of China, Limited Belgrade Branch for construction works, Alstom for transportation systems

Designer: 

Power Construction Corporation of China, Limited and Power Construction Corporation of China, Limited Belgrade Branch for construction works, Alstom for transportation systems

The significance of the project: 

The Line 1 metro project consists of the Makiš Depot and a route 21.3 km long with 21 stations and 13 evacuation and ventilation shafts. The Makiš Depot will manage Lines 1 and 2 of the Belgrade metro. It will serve for the parking of rolling stock for Lines 1 and 2 of the Belgrade metro, as well as for the maintenance of the entire future metro network, which will consist of three lines. Metro Line 1 will connect the currently most traffic-heavy parts of the city.

Status of the project: 

Contract start date: January 10, 2025 (Lot 1 and Lot 2 with Power China), January 12, 2025 (Makiš Depot with Power China). The signing of Lot 3 with Power China and the contract with Alstom is expected in the second quarter of 2025, which will complete the full contracting of Line 1 Phase 1. After the approval of the Preliminary Design for Line 1 Phase 2 by the Republic Revision Commission, the signing of the contract for Line 1 Phase 2 with Power China and Alstom is expected in the second half of 2025.

Investment value: 

-  210,000,000.00 euros excluding VAT- Design and construction of the Makiš Depot (Power China) – 20,340,000.00 euros excluding VATLot 1, Line 1, Phase 1: Design and execution of works, including preparatory activities for the procurement of the TBM (Tunnel Boring Machine) 20,000,000.00 euros excluding VAT Lot 2, Line 1, Phase 1 – Design and Construction Works (Power China). The values of the other contracts listed above will be determined following negotiations with the future Design & Build contractors, Power China and Alstom.

Source of finance: 

Budget of RS and commercial loan

Project description: 

The Line 1 metro project consists of the Makiš Depot and a route 21.3 km long with 21 stations and 13 evacuation and ventilation shafts.