Novi Beograd - Surčin

Project carrier: 

Ministry of Construction, Transport and Infrastructure

Project title: 

Novi Beograd - Surčin

Contracting Authority: 

Government of the Republic of Serbia Ministry of Construction, Transport and Infrastructure of the Republic of Serbia (Financier) PE“Roads of Serbia” (Investor)

Main contractor: 

China Communications Construction Company Ltd.

Investor: 

PE "Roads of Serbia"

Financier: 

Government of the Republic of Serbia, Ministry of Construction, Transport and Infrastructure

Contractor: 

China Communications Construction Company Ltd 

Supervision: 

Corridors of Serbia

Designer: 

Institute of Transportation CIP

The significance of the project: 

The project is of priority importance for the Republic of Serbia, as the section from Novi Beograd to Surčin serves as a connection between the city of Belgrade and the E-763 highway ("Miloš Veliki"), thereby creating a functional whole between the city’s road network and the E-763 highway, which represents the shortest route from Belgrade to the Adriatic Sea

Status of the project: 

The section Novi Beograd – Surčin was opened to traffic on April 1, 2023. The period for remedying the deficiencies listed in the snag list provided by the Engineer is currently in progress. Negotiations are currently underway regarding the execution of additional works related to the connection of the extension of Jurija Gagarina Street to the highway. The specified amendment shall be incorporated in a forthcoming Annex 6 to the Commercial Contract, which will, inter alia, define the contract value for the works and the timeframe for their completion.

Investment value: 

USD 73,8 million

Start of the project: 

Start in 2021

Source of finance: 

RS budget

Project description: 

The state road segment Novi Beograd to Surčin, situated on the left bank of the Sava River, extends approximately 7.9 km in length. It is designed for a design speed of 80 km/h, with gentle longitudinal gradients. The cross-section of the state road ranges in width from 30.7 m to 38.20 m. It is designed with two carriageways, each consisting of three traffic lanes, a central median strip, shoulders on both sides, edge greenery, pedestrian sidewalks, and on one section, two-way bicycle lanes.

For traffic connections with the newly designed roads, in addition to the roundabout at the beginning of the route, three more at-grade intersections and a grade-separated “half-cloverleaf” interchange are planned, connecting to the street leading to the Surčin settlement and the Sava River bank, where the national stadium is planned. Three bridges and three overpasses are planned for crossing watercourses and local roads. Stormwater runoff from the roadway is planned to be managed via a controlled closed drainage system, including treatment before being discharged into receiving bodies, specifically melioration canals.